docs: power: convert docs to ReST and rename to *.rst
Convert the PM documents to ReST, in order to allow them to build with Sphinx. The conversion is actually: - add blank lines and indentation in order to identify paragraphs; - fix tables markups; - add some lists markups; - mark literal blocks; - adjust title markups. At its new index.rst, let's add a :orphan: while this is not linked to the main index.rst file, in order to avoid build warnings. Signed-off-by: Mauro Carvalho Chehab <mchehab+samsung@kernel.org> Signed-off-by: Bjorn Helgaas <bhelgaas@google.com> Acked-by: Mark Brown <broonie@kernel.org> Acked-by: Srivatsa S. Bhat (VMware) <srivatsa@csail.mit.edu>
这个提交包含在:
@@ -22,7 +22,7 @@ the highest.
|
||||
|
||||
The actual EM used by EAS is _not_ maintained by the scheduler, but by a
|
||||
dedicated framework. For details about this framework and what it provides,
|
||||
please refer to its documentation (see Documentation/power/energy-model.txt).
|
||||
please refer to its documentation (see Documentation/power/energy-model.rst).
|
||||
|
||||
|
||||
2. Background and Terminology
|
||||
@@ -81,7 +81,7 @@ through the arch_scale_cpu_capacity() callback.
|
||||
|
||||
The rest of platform knowledge used by EAS is directly read from the Energy
|
||||
Model (EM) framework. The EM of a platform is composed of a power cost table
|
||||
per 'performance domain' in the system (see Documentation/power/energy-model.txt
|
||||
per 'performance domain' in the system (see Documentation/power/energy-model.rst
|
||||
for futher details about performance domains).
|
||||
|
||||
The scheduler manages references to the EM objects in the topology code when the
|
||||
@@ -352,7 +352,7 @@ could be amended in the future if proven otherwise.
|
||||
EAS uses the EM of a platform to estimate the impact of scheduling decisions on
|
||||
energy. So, your platform must provide power cost tables to the EM framework in
|
||||
order to make EAS start. To do so, please refer to documentation of the
|
||||
independent EM framework in Documentation/power/energy-model.txt.
|
||||
independent EM framework in Documentation/power/energy-model.rst.
|
||||
|
||||
Please also note that the scheduling domains need to be re-built after the
|
||||
EM has been registered in order to start EAS.
|
||||
|